![]() Each pipe was driven into the earth until what Jack called refusal. Refusal is the point at which the pile lodged in solid earth and could be driven no further. | I mentioned in a earlier journal posting that I contracted with an engineer to underpinned the southwest corner of my house in three locations. Jack fabricated galvanized steel pipe "pin piles".![]() |
| Then heavy steel support brackets were welded to the top of each pin pile. The corner of the building was jacked-up. I tested the smooth operation of the windows and doors as Jack and Ken lifted the structure. After the lifting the piles were filled with concrete reinforced with a steel bar. Jack and Ken back-fileed the holes and restored the landscaping. I then grouted what remained of the crack between the wall block and painted the wall. After nearly three months of research and only two and a half days of work the project was completed. |