24-MAY-2008
Kitchen Drywall
Drywall is in progress. Will be nice to see it once they get it done early next week.
24-MAY-2008
Exterior is done
This week they finished the siding on the house and started on the drywall. Drywall should be done by Wednesday.
19-MAY-2008
The stone front is done
All but the front door steps are done now. We have to finish the Portico before that can happen. The siding should get put on starting on Wednesday and as long as the weather holds out this week, should be done by the end of the week.
19-MAY-2008
House gets insulation
Now that the framing inspection is done, the insulation got to go in today. As long as all goes well with this inspection, the drywall will start on Wednesday.
07-MAY-2008
Stone front is almost done
Not much exterior work this week due to some rain, but most of the stone is done. Just some odds and ends before the scalfolds can be removed.
05-MAY-2008
Stone gets started
They started putting the stone front on the house yesterday. Looks like it might take another day to get the bulk of it done. The punchout framing work has also been completed as well as most of the electrical and plumbing.
22-APR-2008
Kitchen starts to take some shape
Although it is not much, the lines are starting to show where the future kitchen cabinets will be places. This starts to give an idea of what the kitchen will look like. Still a ways off for now, but its always nice to see some progress. If you look closely enough, you will notice that the window in the picture will have to move a little bit to the right to be where the plans called it to be. Right now, the edge of the cabinets will be in front of it. A little oops that should be taken care of soon.
:: Interior Shots of the house after framing ::
Click on the picture for more pictures of the interior
19-APR-2008
Rear shot of the house from other side
16-APR-2008
No more water in the house
Over the past couple of days the rest of the windows were put in and the roof was put on. I guess we start worrying if we see water in the house from now on out. The stairs were also put in so we now have access to the second floor.
12-APR-2008
End of week Two
This is the end of the second week of framing. Most of the large structure is up. Most of next week will be spent working on the interior details. I am also guessing that the roof will go up to help dry in the house. We had some rain today and we do have a leak problem as it stands right now. :)