28 September 2007 - We've managed to make fair progress this week in spite of the fickle weather. The walls and roof have now been clad and tidied up and the roof underlay is now in place. However, showers today mean that we have been unable to replace the plastic sheeting over the roof whilst we wait for the underlay to dry. The next task is to get the building secure from the weather ready for winter. On our overall timescale I would say that we are 5/6 weeks behind with the work.